NLMK power plant progressing on track, cost overruns
NLMK has not postponed the commissioning of a 300MW utilisation power plant (UTPP), designed to generate electricity from secondary fuel resources, the company tells Kallanish.
Earlier, Russian state media reported the project is postponed to 2024. Investment in the project has increased to RUB 40 billion ($500 million), according to agency Interfax.
“The project is on schedule and there are a few more months of construction,” an NLMK spoke…
This article contains premium data.
It is only available for active subscribers and clients currently
on trial. To continue reading, see the options below.
on trial. To continue reading, see the options below.
Truly global, user-friendly coverage of the steel and related markets and industry that delivers the essential information quickly while delivering on most occasions just the right amount of between-the-lines comment and interpretation for a near real time news service of this kind.
Anonymous
Very good overview of the weekly steel market.
Anonymous