CSN ready to resume Volta Redonda blast furnace
Brazilian steelmaker Companhia Siderúrgica Nacional (CSN) is expected to resume operating blast furnace no.3 at its Volta Redonda plant later this week, media reports in Brazil suggest.
The company has completed maintenance of BF3, which began on 28 June and was initially planned to be completed within 60-days, Kallanish notes.
During the revamp period CSN was supplied by third-party slab, mitigating the impact of this prolonged shutdown on i…
This article contains premium data.
It is only available for active subscribers and clients currently
on trial. To continue reading, see the options below.
on trial. To continue reading, see the options below.
Truly global, user-friendly coverage of the steel and related markets and industry that delivers the essential information quickly while delivering on most occasions just the right amount of between-the-lines comment and interpretation for a near real time news service of this kind.
Anonymous
Very good overview of the weekly steel market.
Anonymous